Thursday, 1 May 2014

Day 1, Bukit Panjang

For the month of May, we will be scheduling an update for each station along Stage 2 everyday. Starting with Contract 912 for the construction of Bukit Panjang station and the associated C&C tunnels north and south of the station.
C912 Zone 2 (station)
Overview of Bukit Panjang station
C&C tunnels to Gali Batu Depot
South-North view of station, which has nearly been completely backfilled
500m radius terminal crossover tunnel south of BKP (Zone 1)
Service walkways leading to the circular shafts where the ventilation building will be built
Twin flyover columns in the background
Cut and Cover tunnels starting from the north end of BKP,  flyover pillars in the background
C&C tunnels heading north towards Gali Batu
Aerial View of C&C tunnels (Zone 3)
Aerial View of C&C tunnels (Zones 4&5)
Beneath the surface
Backfilling in progress
Roof Slab has been casted
Works on the flyover landing would commence after the C&C is covered
Sequence of direct backfilling (1)
Sequence of direct backfilling (2)
Sequence of direct backfilling (3)
Sequence of direct backfilling (4)

Backfilled layer
Backfilling with the use of a lorg arm excavator

No comments:

Post a Comment

Note: only a member of this blog may post a comment.