Day 10, Stevens

Stevens station. The entrance pit has just recently been formed and concreted. From now, the station will progressively take shape at the surface following the construction of stairs and subsequent installation of escalators. Below is a photo timeline of the construction progress taken over the last 3 years.

Piling and Trench Cutting works mid 2011
Excavation works started to commence early 2012 following the drive of the remaining king posts
Late 2012. Gantry cranes were brought in to facilitate top-down movements due to site constraints.
Overview of Stevens Station - as it is now in May 2014
Close up of excavation pit 3
Close up of the entrance
Close up of the entrance


Future interface with TSL beneath Stevens Road