Tuesday, 31 May 2016

Downtown Line 3 May/Jun 2016 Update: Part 2

As promised, here is part 2 of the DTL3 construction update featuring DT28 to DT35. Stay tuned for our next update!

DT28 - Kaki Bukit
Kaki Bukit Ave 1 was reinstated on 24th Apr 2016. Surface structures are at the final stage of completion.

Tuesday, 28 October 2014

Expo's roof slab

On Deepavali 2014, the team was busy running around gathering some updates and information to bring to you. We start at the eastern end with Expo station where works, as rightfully should be, were fully underway. The Samsung team here has made decent progress and the roof slab for some parts of the station is being done. It seems that original plans for the station have been modified and it would now include a paid linkway to the Changi Airport Line station. Most part of this station is built via the top-down method which means that casting of the station structure starts at the bottom. To have the structure near the top being built, it means that the basic structure is at a fairly advanced stage of construction.

Expo station site looking towards the over run tunnel and Expo facility building.

Sunday, 20 April 2014

Brief overview of Stage 3 in 1st Quarter

It is already coming to the end of April, so we'll just cover the stage in brief for the first quarter of the year in this post, taking a look at some updates from the station sites today. Starting with the terminal point at Expo.

Expo
The station has been fully excavated and work now progresses on to the structure itself. Rebar is first installed and then concrete is poured to form the structural skeleton of the station. Currently, work is focused on the platform and under-platform levels.

A view of the work area for the future exit next to the Singapore Expo foyer.

Tuesday, 26 November 2013

Expo update from October

Some photos to share of Expo station from last month.

25 October 2013

Thursday, 7 November 2013

Expo update

Expo station is sandwiched between several developments and has a pretty dramatic look to the construction site. Excavation goes on pretty close to the Changi City Point, with some parts of the walkway literally at the edge of the temporary earth retaining system (diaphragm walls). Take a walk down memory lane as we recap how the site has changed and progressed over the years.

27 November 2011 - Downtown Line 3 ground breaking was at Expo
station site

27 November 2011 - The end of the ceremony saw the BC Cutter being
unveiled for the grand finale where the guest of honour commenced work
21 April 2012 - Excavation proper has yet to begin with diapghragm
wall works taking place first

21 April 2012 - The EWL above needs to be under-pinned
09 May 2013

09 May 2013

09 May 2013

09 May 2013
03 July 2013

03 July 2013

03 July 2013

03 July 2013

03 July 2013

03 July 2013
24 October 2013

24 October 2013

24 October 2013