Sunday, 4 May 2014

Day 4, Hume

There haven't been any signs of any structures appearing at the surface of Hume station. At this point, works have progressed that the roof slab has been cast. Contract 915 also involves the construction of all 4 tunnels leading out of the future station - currently built as a box structure to be topped off at a later date. Final breakthrough at Hillview and Beauty World were achieved by TBM2 and 1&3 in April and June respectively last year. Trackworks are on going between Hume and Beauty World from the Gali Batu staging area.







No comments:

Post a Comment

Note: only a member of this blog may post a comment.