Sunday, 27 September 2026

DTL2e - A recap in August 2026

 

An overview of new renders released for DE1 station and the site progress at the DE2/NS6
interchange in August 2026.

With the award of all 4 civil contracts for the Downtown Line 2 Extension (DTL2e), advanced works were progressing and works on the main contracts were commencing. Over at the sites of the two stations, clearing works as part of the advanced contract were still underway. Works under main contract 991 for the construction of connecting tunnels between DE1, DE2 and Gali Batu depot however were about to kick off proper.

Monday, 1 June 2026

DTL - A snapshot in May 2026

An overview of the Downtown Line extension project sites as of May 2026.
Top (L - R) : DT36 - Xilin, DE01 - Intermediate station
Bottom (L - R) : DE02 - Sungei Kadut, Contract 993 tunnel docking shaft

It's hard to believe, as it only feels like yesterday that the line opened, but the Downtown Line (DTL) has been around for 13 years this December. 13 years on and the line is being extended at both ends, adding a further 6.2km to the 40km-long line. As one extension project reaches the finish line, another begins the arduous process. We check in at both projects to see how progress is going - details after the jump.

Thursday, 19 February 2026

Contracts 990 & 992 - Next two DTL2e civil contracts awarded

Summary of DTL2e contracts.

Today, the Land Transport Authority (LTA) successfully awarded 2 contracts for the Downtown Line 2 extension (DTL2e). The two contracts will see the completion of two stations along the extension, one of which will serve as an interchange with the North-South Line (NSL).

Saturday, 6 September 2025

DTL2e - A snapshot in August 2025

While contract tendering for the 4 civil contracts continues for the Downtown Line 2 Extension (DTL2e), work has commenced on advanced site preparation in the form of demolition works. Contract 9177, awarded to Woh Hup Engineering Pte Ltd, has seen the hoarding up of several factories within the Sungei Kadut project corridor. We take a look at the progress made and views around the 2 future stations after the jump.

Sunday, 15 June 2025

DTL - A snapshot in May 2025

An overview of the various Xilin station exits and facilities at street level in May 2025.

We're here to cover an update on progress along the Downtown Line's extensions - both to the east & the west. In the east, progress is becoming more apparent at street level & we also have a sneak peak at the station's interior. Over at the west, the pre-qualification period has ended for the extension's 4 contracts. Who has been qualified to bid for the contracts? Find out all that and more after the jump!

Wednesday, 26 March 2025

DTL2e - Final civil contract floated

 

Contract 993 tender details.

Today, the Land Transport Authority (LTA) floated the final civil contract tender for the Downtown Line 2 extension (DTL2e) - contract 993. This contract will see the construction of twin bored tunnels from the DE1 Intermediate station to the existing DTL main line tunnels. A docking shaft will be built as part of the contract near the junction of Senja Way and Woodlands Road.

Monday, 17 February 2025

DTL - A snapshot in February 2025

An overview of the various Downtown Line projects on-going.
Top (L - R): DT36 - Xilin, DT4 - Hume
Bottom (L - R): DE1 Intermediate station, DE2/NS6 - Sungei Kadut

This month, we have a much more comprehensive snapshot update for the Downtown Line (DTL) covering the phase 3 extension, phase 2 extension and the in-fill station at Hume before it opens. With lots to cover in this update, let's get to it - you'll find pictures and information after the jump.