02 February 2014 |
02 February 2014 |
02 February 2014 |
02 February 2014 |
02 February 2014 |
The second exit is also taking shape, outside the Land Transport Authority headquarters. A ventilation shaft will be integrated with this exit which is expected to be barrier-free accessible.
02 February 2014 |
Back-filling work on covering up the transfer linkway has also been largely completed. The linkway now lies fully buried under earth and some parts of recycled concrete.
02 February 2014 |
02 February 2014 |
In line with the future North South Expressway running under Bukit Timah Road, the Rochor canal is being rebuilt above the roof slab of the Little India station as well. This is taking shape rapidly and once completed, will allow the back-filling above the station to commence. A further road diversion may have to wait until trackworks are completed.
02 February 2014 |
02 February 2014 |
And lastly, piling works are going on at the existing NEL exit C for the new lift access.
02 February 2014 |
02 February 2014 |