December tunnel chart for DTL2 |
C918A |
C921 |
An overview of the progress of the remaining 5 tunnels for stage 2:
C918A
S604 at 356 rings (~55% completed)
S605 at 73 rings (~11% completed)
C921
S608 at 41 rings (~20% completed)
Will try and get updates for the last 2 tunnels under C917A.
No comments:
Post a Comment