Thursday, 12 December 2013

DTL2 December tunnel progress

December tunnel chart for DTL2

C918A
C921

An overview of the progress of the remaining 5 tunnels for stage 2:

C918A
S604 at 356 rings (~55% completed)
S605 at 73 rings (~11% completed)

C921
S608 at 41 rings (~20% completed)

Will try and get updates for the last 2 tunnels under C917A.

No comments:

Post a Comment

Note: only a member of this blog may post a comment.