12 December 2010 - Road diversion works at the Eng Neo Avenue junction in full swing |
12 December 2010 - Many storage containers sitting on the original alignment of Bukit Timah Road |
08 May 2011 - Construction site hoarding along Bukit Timah Road to construct the diaphragm walls |
08 May 2011 - The u-turn before the Eng Neo Junction was kept open through most of the diaphragm wall works |
08 May 2011 - Clam-shell grabbing machine on site at the Eng Neo junction |
08 May 2011 - Used augers for secant bored pile works, usually where the TBM will breakthrough |
13 March 2012 - Secant bored pile works going on |
13 March 2012 - Struts being installed |
16 December 2012 - Reception shaft for TBM S-617 from Tan Kah Kee |
16 December 2012 |
16 December 2012 |
16 December 2012 |
16 December 2012 |
16 December 2012 |
16 December 2012 |
16 December 2012 - 6 layers of struts here |
16 December 2012 |
No comments:
Post a Comment