Fittings at the Beauty World station are almost completed. The hoisting and installation of glass panels commenced at the start of last month on Entrances A and B, and have completed since then. Entrance C's roof has been covered with an aluminium sheet and should commence architectural fittings soon. The network of covered linkways surrounding entrance B have been structurally completed.


Entrance B


































Platform of Beauty World (Photo cr: Lito)