Architectural works have almost completed at the 2 stations. Reinstatement to the surface at Little India has completed, and the temporary road deck above the canal has been demolished. The subsequent demolishment of the old canal is expected to be handled by the NSE contractor within the next 2 years.

Reinstatement is taking place at Rochor similarly, with the intersection between Rochor Canal Road and Bencoolen St realigned. The retrieval shaft at Queen Street has also been reinstated back. Photos in this update were taken from SSangyong's facebook page prior to June.


The box tunnel for the future North South Expressway (NSE) runs above the roof of the Rochor Station 
Artwork installation surrounding the lift shaft within Rochor Station

April 2015 - Rochor main entrance
May 2015


April 2015
May 2015

April 2015
May 2015 (the intersection has since been reinstated)
Temporary reinstatement near Ophir Road. The NSE project will commence by next year.
TBM retrieval shaft at Queen St - April 2015 reinstatement
May 2015


 Little India



April 2015
May 2015




Prior to reinstatement
Prior to reinstatement - April 2015
Second entrance
Realignment - May 2015