Tuesday, 28 April 2015

Sixth Avenue - Beam Launching


The beam launching works that are scheduled tonight for the new POB at the Sixth Avenue Station is testimonial to the C917A project team's commitment and efficiency towards a swift completion of the Downtown Line 2. The first truss segment, to be launched over Bukit Timah Road tonight, comes just less than 2 weeks after the twin columns were cast.

The second truss segment across the canal and Dunearn Road will be launched up next Tuesday (May 5).

April 30 - Beam launched over Bt Timah Road
May 8 - Beam launched over Dunearn Road

Apr 28 - view from Dunearn Road
Apr 28 - View from Bt Timah Road
April 29 - Lifting of first span
April 30
April 30
May 8
May 8
May 8
May 8
May 8