The 918A project team is currently preparing to stage a road diversion at the Tan Kah Kee station. The diversion is necessary for the remaining columns of the POB on the Bukit Timah bank to be piled and erected. Piling works for the POB columns along the Dunearn bank had just completed last week. Escalators have also been lowered down the main entrance, with BSC targeted by March or April. The roof slab can also be seen at the former launch shaft.
The construction team will continue working through the weather, round the clock for the next 48 hours to complete the diversion by the weekend.
|
Casting works on going along the realignment |
|
Render of the constructed columns on the Bukit Timah bank that the diversion is catering for |
|
Roof Slab at the launch shaft. 2 ventilation buildings will subsequently be erected here |
|
Completed piling works along the Dunearn bank |
|
Entrance B at Watten Estate |