C937 - Breakthrough of TBM 2 at Chinatown on Mar 24 |
C917A |
Closure of centre carriageway to conduct SI |
S602 has resumed tunnelling though the battle against ground is not in their favour. Downstream along Maple Ave MacDow is conducting SI along lane 3 in anticipation of granite currently challenged by its sister TBM.
S603 at 710 rings (Mar 20, ~72% completed)
TBM has slowed down to 1 ring per day. It is crossing the 2nd diversion canal at the moment, concluding the end of the section weakened by granite. Cutterhead is being replaced every 3-4 days. This is alike the challenge faced by STEC's TBM1 near Stevens station last year. The tunnel route is expected to be trouble-free from here till breakthrough point at SAV, exception of another possible section of granite lying below the junction of Sixth Avenue.
C918A |
S605 crossing the canal beneath the Farrer Flyover |
S605 at 446 rings (Mar 19, ~66% completed)
TBM has paced down. Breakthrough together with S603 should only take place in May.
Remaining gantry crane standing on site |
With thanks to Stefano for his contribution.