Tuesday, 26 May 2015

Acoustic Shed Dismantles

Dismantling of the temporary acoustic shed at the King Albert Park site commenced at the start of this month. A mobile crane and cherry picker is currently facilitating the dismantling, with the inner section of the shed closer to Maplewoods being dismantled first. The side barriers are being removed concurrent with the dismantling of the roof.

Entrance B has achieved BSC, and the escalators had just been fitted into the structure over the weekend.



Monday, 25 May 2015

Sheet Piling at Hume

Sheet piling works have been carried out on both sides of the road over the past 2 months. The sheet piles form an earth retaining structure for the subsequent excavation of the additional 2 structures that would extend from the existing station box. An integrated superstructures of the entrances and ventilation buildings would likely surface by the end of this year. There is a possibility that this station would open sooner than anticipated, perhaps even by the next decade, judging by the late decision of the additional works.


Hume site, May 2015

Sunday, 24 May 2015

Little India Realigns

Little India progresses onward as the next station to complete reinstatement works on the surface. The permanent realignment of the southbound Bukit Timah Road was implemented earlier this morning. The temporary road decking above the old canal will be subsequently demolished alongside the former Rochor Canal.


Realignment as of 7am (Photo Cr: Aran)