Friday, 4 September 2015

Hillview Station

The last 6 beams for the new flyover at Hillview were launched up at the end of August, concluding all beam launching works at the site. Reinstatement works have commenced along the northbound road and we project the new road to open by the end of this week. The southbound road had already diverted to its permanent alignment sometime back. The new flyover should open by October.

Architectural works have completed on the vent shafts, cooling tower and entrance along the southbound road. The northbound entrance will complete the final touch ups such as the covered linkways and bus stops upon the realignment of the northbound road. The V-shaped intersection between Hillview Avenue and UBTR will also be reinstated for right turning vehicles town-bound.


Reinstatement for the northbound carriageway beneath the flyover