Tuesday, 30 June 2015

Little India & Rochor

Architectural works have almost completed at the 2 stations. Reinstatement to the surface at Little India has completed, and the temporary road deck above the canal has been demolished. The subsequent demolishment of the old canal is expected to be handled by the NSE contractor within the next 2 years.

Reinstatement is taking place at Rochor similarly, with the intersection between Rochor Canal Road and Bencoolen St realigned. The retrieval shaft at Queen Street has also been reinstated back. Photos in this update were taken from SSangyong's facebook page prior to June.


The box tunnel for the future North South Expressway (NSE) runs above the roof of the Rochor Station 

Tuesday, 9 June 2015

Tunnelling Completes for Downtown Line

The final Tunnel Boring Machine under C926 docked into Tampines West station from the Prison Shaft yesterday, completing the 42km long Bukit Panjang bound tunnel for the Downtown Line.


Completion of all bored tunnels under DTL3 on June 8, 2015

Monday, 8 June 2015

Tan Kah Kee - Structural Completetion

Casting of the escalator frame at the TKK POB linkway completed over the weekend. This is one of the final major structural components to be completed at the site. Fitting works have commenced on Entrance B, while steel frames for the roof have been installed on the bridge. The final set of escalators for the DTL2 will be delivered and fitted into the linkway between the bridge and the main entrance this month.

Structural completion of the transfer linkway connecting the POB and the main entrance